HOA approval for a remodel: what it does to the start date
Your client has paid a deposit and expects demolition to start, but the association has not approved the new bathroom window. HOA approval for a remodel can move the start window, affected material orders, and crew booking; make written approval a dated condition before promising the start. This guide gives you an application checklist and agreement wording you can use this week.
Interior-only work may not need association approval. A project called a bathroom remodel may still include an exterior vent, a changed window, or work affecting shared building systems. Do not guess which house you are quoting. Get the actual scope and the association’s requirements in front of you.
HOA approval for a remodel is a separate yes
The architectural review committee is not the building department. Its decision concerns the association’s requirements for the proposed work. The city or county handles its own permit requirements. Your crew calendar answers a third question: when you can actually do the job.
Keep those answers separate when you talk to the client. “Approved” is too loose a word when it could mean the client accepted the quote, the city issued a permit, or the association accepted an exterior change. Name the approval and the work it covers.
| Item to confirm | What it settles | What to keep in the job record |
|---|---|---|
| Association requirements | Whether this scope needs association review | Applicable rules and written scope clarification |
| Association decision | Whether the submitted work is approved, including conditions | Decision and the drawings or specifications it references |
| City or county permit | Local permission for work requiring a permit | Permit and approved plans, where required |
| Crew availability | When the contractor can perform the cleared scope | Current start window and remaining dependencies |
For the local permit question, see Do you need a permit for a bathroom remodel in Washington?. An association decision does not answer that question.
For the scheduling conversation after a deposit, see Remodel lead time: what to tell a client who already paid. Paying a deposit does not settle either approval dependency.
Check the scope before calling it interior-only
Ask the owner for the declaration or CC&Rs, current architectural guidelines, and alteration application instructions. Ask who can confirm whether the proposed work requires review. The person collecting the form may have a different role from the person authorized to decide.
Describe the physical changes. “Bathroom renovation” tells the reviewer less than “replace fixtures in their existing locations, enlarge the exterior window, and add a wall-mounted exhaust termination.” That description lets everyone see which part of the project needs an answer.
Exterior appearance deserves a specific check. For example, Washington’s condominium statute RCW 64.34.240 makes exterior appearance and common-element appearance changes subject to association permission for condominiums governed by that provision. It also qualifies alterations by reference to the declaration, other law, and effects on structure or building systems. That is a reason to check the governing documents, rather than apply one rule to every HOA or condo. Source: Washington Legislature.
Use this scope check during the site visit:
- Will any window, door, siding, roof surface, exterior color, or visible equipment change?
- Will the work add or move a vent or other exterior penetration?
- Could it affect shared plumbing, structure, or another common element?
- Do the documents address interior alterations or construction access?
- Who will give a written answer about this exact scope?
These questions identify what to investigate. They do not establish that approval is required. If review is unnecessary, keep the written clarification with the scope it describes. A later change to that scope needs another check.
Build the application around the actual work
Start with the association’s own instructions. Use the following as a preparation checklist, then remove or add items to match its requirements. Do not present a generic contractor checklist as the association’s official form.
A useful HOA remodel application packet may need:
- Property address and owner contact details.
- A plain description of existing conditions and proposed changes.
- Drawings showing dimensions and locations of affected work.
- Photos identifying the existing exterior condition.
- Product details, finishes, and colors for visible changes.
- Contractor information and any requested supporting documents.
- Proposed construction arrangements, if the association asks for them.
Give drawings a date or revision label. Use the same product description in the quote and application. If the packet says one window finish and the supplier order says another, approval of the packet does not resolve that mismatch.
Assign submission responsibility before the client leaves the meeting. For example: the owner submits the application, the contractor supplies the window drawing, and the owner forwards requests and decisions to the contractor. If you agree to do more, write down that added responsibility.
Then distinguish receipt from review. All-In-One Community Management describes an initial completeness check before an application reaches committee review. Its published process also distinguishes approval, conditional approval, and a declined request. Those are details of its process, not a universal timetable, but they show why an upload confirmation is insufficient evidence of approval. Source: All-In-One’s architectural review process.
Ask the association whether the packet is complete, what remains outstanding, and which review procedure applies. Use its answer to update the schedule. Do not invent a typical review period or turn a meeting date into a promised decision date.
Put the approval deadline beside the start window
The agreement should connect the planned start to a named approval deadline. “Subject to HOA approval” leaves the client without a clear date or consequence.
Here is a sentence to adapt to the job and your agreement:
The planned start window of [start date] through [end date] assumes that the owner provides written association approval for [specific scope] by [approval deadline]; if that approval is late or refused, the start window moves, and the contractor will confirm a revised window after the required approval and any resulting scope changes are resolved.
Name the affected scope instead of writing only “the remodel.” Fill in actual dates before sending it. The approval deadline is your scheduling condition, not a promise that the committee will respond by then.
Agree separately on responsibility for submission, revisions, and any charges. If you want late approval to have a particular cost consequence, that needs its own reviewed agreement language. The scheduling sentence alone does not settle deposits, cancellation rights, or delay charges.
PikeBuild can hold the date and condition in the agreement text. It does not file with the association. The owner and contractor still need to assign that work and obtain the decision.
Worked example: the bathroom window holds the start
This is an illustrative schedule, not a customer result or an estimate of committee review time.
The owner accepts a bathroom quote that includes a larger exterior window. The agreement lists a planned November 16–20 start window, conditional on written association approval by November 6. The window drawing submitted for review matches the quoted size and finish.
On November 6, the owner has a submission receipt but no decision. Under the agreed scheduling condition, the original window is no longer confirmed. The contractor checks crew availability rather than leaving the client to assume Monday demolition is still booked.
On November 10, written approval arrives with a condition requiring a different exterior finish. The contractor checks the revised product, supply timing, and any effect on price before confirming a new start window. The job has an approval, but the condition still needs to be reconciled with what will be installed.
Send a message when the deadline is missed:
Subject: Bathroom start window and association approval We planned to start November 16–20, assuming written association approval for the larger window reached us by November 6. We have the submission receipt, but we still need the decision covering that window. The planned start window now needs to move under that condition. Please forward the decision and any conditions when they arrive. I’ll check the approved window details, supply timing, and crew availability, then send you a revised start window. I’ll update you again on November 10, even if the decision is still pending.
The client gets a reason, a specific missing item, and the next update date. You have not blamed the committee or promised a replacement start you cannot support.
Read the decision before releasing the job
Match the decision to the property, application, and drawing revision. Check whether it covers every affected item. Read conditions before treating “approved” as permission to build the quoted scope unchanged.
If a condition changes a product, location, or finish, reconcile it with the client and supplier. Document any agreed scope or price change through your usual change process. If the decision refuses the proposed work, agree on the next scope before rebuilding the schedule.
Treat silence carefully. Whether a missed response deadline has a legal effect depends on the applicable law and documents. Do not make that determination from a generic internet rule. If the owner claims the work is approved by default, have them resolve that basis with the association or their adviser before you rely on it for mobilization.
You may be able to start an independent portion of the work while another portion waits. Before offering that option, check permits, sequencing, access, and whether the pending decision could change work you are about to perform. Put the revised sequence and its limits in writing. Starting demolition simply to show progress can leave the client with an unusable room while the actual dependency remains.
Give the client a dated status, even without a decision
Choose a regular update day and keep it while approval is outstanding. This is your communication cadence, not the committee’s review schedule.
Each update should name the current status, the missing item, who is pursuing it, and when you will report again. “Waiting on HOA” is less useful than “The owner submitted the revised window drawing; we are waiting for written confirmation that the packet is complete.”
Once the decision arrives, update the start window against the approved scope, required permits, materials, and available crew. Keep the earlier messages so both sides can see why the date changed.
Sources
- Washington Legislature: RCW 64.34.240, alterations of condominium units. Supports the distinction between qualifying unit alterations and exterior or common-element appearance changes for condominiums governed by this provision.
- All-In-One Community Management: architectural review process. Provides a real example of completeness checks and different decision outcomes. Its requirements and timing are specific to the applicable association.
For your next step, see AI on a leash for client email drafts you review before sending.